Project Name: Twin Ridge Elementary School Renovation
Location: 1106 Leafy Hollow Circle Mt. Airy, MD 21771
Project Goal: Twin Ridge Elementary School (TRES) is to be renovated within the Summer 2026 and the summer of 2027. The project will focus on revitalizing interior and exterior aesthetics, roofing needs, HVAC/Electrical and Plumbing upgrades as required to increase the longevity of the school for another 35 years. The construction will solely focus on upgrading systems and aesthetics and will not change/increase any programmatic space. The project is being designed by Ashley-McGraw Architects and the work will be performed by Davis Construction. The team will meet all current local building codes of the Authority Having Jurisdiction and the FCPS Educational Program Specifications.
Current Status: Design
Overall Progress: Site Survey and Design
One Month Look Ahead:
- Schematic Design Submission and presentation on November 5th
Estimated Completion Date:
- Phase 1 - August 2026
- Phase 2 - August 2027